The Collapse of the Alto Río Building during the 27 February 2010 Maule, Chile, Earthquake
Issue Date
2012-06Author
Song, Cheng
Pujol, Santiago
Lepage, Andrés
Publisher
Earthquake Engineering Research Institute
Type
Article
Article Version
Scholarly/refereed, publisher version
Metadata
Show full item recordAbstract
The Alto Río Building, a 15-story building located in Concepción, Chile, collapsed during the 2010 Maule earthquake. Construction of the building was completed in 2009 following the Chilean building code of 1996. The building was provided with reinforced concrete structural walls (occupying nearly 7% of the floor area) to resist lateral and vertical loads. The walls failed in the first story, causing the overturning of the entire building. This paper provides detailed field observations and discusses plausible causes of the collapse.
Description
This is the published version. Copyright 2012 Earthquake Engineering Research Institute
Collections
Citation
Cheng Song, Santiago Pujol, and Andrés Lepage (2012) The Collapse of the Alto Río Building during the 27 February 2010 Maule, Chile, Earthquake. Earthquake Spectra: June 2012, Vol. 28, No. S1, pp. S301-S334. http://dx.doi.org/10.1193/1.4000036